5. As part of the sensitivity analysis of the effect of the new project on the company's cost of capital, Sandell is estimating the cost of equity of the China project considering that the China project requires a country equity premium to capture the risk of the project. The cost of equity for the project in this case is closest to:
选项:
A. 10.52 percent.
B. 19.91 percent.
C. 28.95 percent.
解释:
C is correct.
re = 0.0425 + 3.686(0.0482 + 0.0188) = 0.2895 or 28.95%