开发者:上海品职教育科技有限公司 隐私政策详情

应用版本:4.2.11(IOS)|3.2.5(安卓)APP下载

lululala · 2021年10月23日

最优价值

* 问题详情,请 查看题干

NO.PZ201601200500000804

问题如下:

4. What is the NPV (C$ millions) of the optimal set of investment decisions for Society Services including the expansion option?

选项:

A.

6.34.

B.

12.68.

C.

31.03.

解释:

B is correct.

Assume we are at time = 1. The NPV of the expansion (at time 1) if demand is "high" is

NPV=190+t=19401.10t=C$40.361millionNPV=-190+\sum_{t=1}^9\frac{40}{1.10^t}=C\$40.361million

The NPV of the expansion (at time 1) if demand is "low" is

NPV=190+t=19201.10t=C$74.820millionNPV=-190+\sum_{t=1}^9\frac{20}{1.10^t}=‐C\$74.820million

The optimal decision is to expand if demand is "high" and not expand if "low."

Because the expansion option is exercised only when its value is positive, which happens 50 percent of the time, the expected value of the expansion project, at time zero, is

NPV=11.100.50(40.361)=C$18.346millionNPV=\frac1{1.10}0.50(40.361)=C\$18.346million

The total NPV of the initial project and the expansion project is

NPV = –C$5.663 million + C$18.346 million = C$12.683 million

The optional expansion project, handled optimally, adds sufficient value to make this a positive NPV project.

请问行权的时候不就是最优价值了吗?为什么最后还要加上没有option的原始NPV呢?谢谢!

1 个答案

王琛_品职助教 · 2021年10月26日

嗨,从没放弃的小努力你好:


因为 optional expansion project,是在 original project 的基础上产生的后续项目,没有开始的期初投入,就没有第一年末的追加投入选择哈

题目是问含权项目的 NPV,所以要加上 original project 的 NPV

----------------------------------------------
努力的时光都是限量版,加油!

  • 1

    回答
  • 0

    关注
  • 964

    浏览
相关问题

NO.PZ201601200500000804 12.68. 31.03. B is correct. Assume we are time = 1. The NPV of the expansion (time 1) if manis \"high\" is NPV=−190+∑t=19401.10t=C$40.361millionNPV=-190+\sum_{t=1}^9\frac{40}{1.10^t}=C\$40.361millionNPV=−190+∑t=19​1.10t40​=C$40.361million The NPV of the expansion (time 1) if manis \"low\" is NPV=−190+∑t=19201.10t=‐C$74.820millionNPV=-190+\sum_{t=1}^9\frac{20}{1.10^t}=‐C\$74.820millionNPV=−190+∑t=19​1.10t20​=‐C$74.820million The optimcision is to expanif manis \"high\" annot expanif \"low.\" Because the expansion option is exerciseonly when its value is positive, whihappens 50 percent of the time, the expectevalue of the expansion project, time zero, is NPV=11.100.50(40.361)=C$18.346millionNPV=\frac1{1.10}0.50(40.361)=C\$18.346millionNPV=1.101​0.50(40.361)=C$18.346million The totNPV of the initiprojeanthe expansion projeis NPV = –C$5.663 million + C$18.346 million = C$12.683 million The optionexpansion project, haneoptimally, as sufficient value to make this a positive NPV project.请问老师,40/1.1^t t=9,这个计算器怎么按啊?还是要一个一个按,按9个?

2021-07-29 16:45 2 · 回答

NO.PZ201601200500000804 12.68. 31.03. B is correct. Assume we are time = 1. The NPV of the expansion (time 1) if manis \"high\" is NPV=−190+∑t=19401.10t=C$40.361millionNPV=-190+\sum_{t=1}^9\frac{40}{1.10^t}=C\$40.361millionNPV=−190+∑t=19​1.10t40​=C$40.361million The NPV of the expansion (time 1) if manis \"low\" is NPV=−190+∑t=19201.10t=‐C$74.820millionNPV=-190+\sum_{t=1}^9\frac{20}{1.10^t}=‐C\$74.820millionNPV=−190+∑t=19​1.10t20​=‐C$74.820million The optimcision is to expanif manis \"high\" annot expanif \"low.\" Because the expansion option is exerciseonly when its value is positive, whihappens 50 percent of the time, the expectevalue of the expansion project, time zero, is NPV=11.100.50(40.361)=C$18.346millionNPV=\frac1{1.10}0.50(40.361)=C\$18.346millionNPV=1.101​0.50(40.361)=C$18.346million The totNPV of the initiprojeanthe expansion projeis NPV = –C$5.663 million + C$18.346 million = C$12.683 million The optionexpansion project, haneoptimally, as sufficient value to make this a positive NPV project.为何不是在0时刻看,有两种情况 需求低,只投了190,不追加投资,npv为负 追加投资190,需求高,npv为正然后将两种情况各0.5加权求和?现在答案只考虑了第二种情况加权0.5,为何不第一种情况也加权0.5加在一起呢

2021-04-17 16:10 1 · 回答

为什么现金流要乘以0.5呢?即使PROBABILITY是50%,但是这个不是应该假设已经是OPTIMAL了吗,为什么还需要考虑概率。谢谢!

2020-06-04 11:09 1 · 回答

12.68. 31.03. B is correct. Assume we are time = 1. The NPV of the expansion (time 1) if manis \"high\" is NPV=−190+∑t=19401.10t=C$40.361millionNPV=-190+\sum_{t=1}^9\frac{40}{1.10^t}=C\$40.361millionNPV=−190+∑t=19​1.10t40​=C$40.361million The NPV of the expansion (time 1) if manis \"low\" is NPV=−190+∑t=19201.10t=‐C$74.820millionNPV=-190+\sum_{t=1}^9\frac{20}{1.10^t}=‐C\$74.820millionNPV=−190+∑t=19​1.10t20​=‐C$74.820million The optimcision is to expanif manis \"high\" annot expanif \"low.\" Because the expansion option is exerciseonly when its value is positive, whihappens 50 percent of the time, the expectevalue of the expansion project, time zero, is NPV=11.100.50(40.361)=C$18.346millionNPV=\frac1{1.10}0.50(40.361)=C\$18.346millionNPV=1.101​0.50(40.361)=C$18.346million The totNPV of the initiprojeanthe expansion projeis NPV = –C$5.663 million + C$18.346 million = C$12.683 million The optionexpansion project, haneoptimally, as sufficient value to make this a positive NPV project.扩张项目的PVCF1已经得出,为什么折现一期的PV就是NPV?能不能用老师说的画图作差法再一下?

2020-03-30 06:03 1 · 回答