问题如下:
Enterprise risk management(ERM)is the process of managing all corporation risks within an integrated framework. Which of the following options is not one of the contents of ERM?
选项:
A.Risk assessment for every project should be centralized.
B.The planner of the project conducts a preliminary assessment of the project risks.
C.Regularly assess the performance of each business unit and measure the impact of each business unit on the total risk.
D.The firm will accept the project only when the project's return is larger than the contribution cost of the project to the firm's total risk.
解释:
A is correct.
考点:Effective ERM的特点
解析:ERM要求的是decentralizing risk management, 是为了保障每个项目的总风险都被项目经理在内部评估中完整的评估出来。集中评估不满足这个目的。
老师好,能否帮忙对比讲解一下这道题的A答案,以及下面这道题的C答案。下面这道题是Section 4的题目。谢谢!