问题如下:
Company M has a four-year project with an expansion option, which depends on the demand at the end of the 1st year. Whether demand is -high- or -low- in Years 1–4 will be determined during the first year. The probabilities of -high- or -low- demand are equal. The cost of capital is 12%. We should notice that the expansion option will not exist if the initial investment is not made. The detailed information of the project is given in the following tables.
The initial project:
Additional cash flows with the optional expansion project:
What’s the NPV of the initial project without the real option?
选项:
A.$2.57 million
B.-$13.32 million
C.-$16.28 million
解释:
B is correct.
考点:Evaluating Projects with Real Options
解析:不考虑实物期权的情况下
NPVhigh = -150 + = $32.24 million
NPVlow= -150 + = -$58.88 million
Expected NPV = 0.50(32.24) + 0.50(-58.88) = – $13.32 million.
请问如果把现金流直接按照45计算,计算过程是什么呀?谢谢