问题如下图:
选项:
A.
B.
C.
解释:
啊啊啊,这个D1到底是2.5还是2.5*(1+5%),有的题目乘以1+g,有的题目没有,搞不清楚啊啊啊,有的答案是不是有问题啊啊啊
发亮_品职助教 · 2018年11月14日
用GGM模型算Equity的Required return时,分子的Dividend是下一期的Dividend,对应的标识是D1;
题干描述的是:the expected dividend next year is 2.5
所以这个2.5就是D1,直接代入上面的GGM变形公式;
有的题目给定的是现在时刻的Dividend,即D0;所以要分子要带 D1= D0×(1+g)
一定要注意题干描述的是哪个时期的Dividend;
比如下面这道题给的就是D0
所以如果这道题要用GGM算Required return的话,分子需要用:2×(1+g)
NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 我不太能理解为什么第一步的Re是用2.5/50+0.05,请问这是在哪里学的?
NO.PZ2016021706000031问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039.B.$91,236.C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 老师我想问一问,这道题能不能用计算机cf的功能来算出来,只不过是CF0是10300,剩下的I是Wacc这样,谢谢
NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 这道题感觉有点问题根据债和股的比例能知道股占了40%,总共投入了10w那么能算出多少股股数知道了能算出f,不就应该用f那个公式而不是r=P +G
NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 老师所以这道题考的是flotation metho的知识点是吗? 所以只要题目说flotation cost 是个具体的金额,就是考察 metho2 也就是preferreapproach?
NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costis $3000 for the equity of this project. What's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 为什么这里的分母50,不需要减去F?不是应该2.5/50-3000+0.05吗