Enterprise risk management(ERM)is the process of managing all corporation risks within an integrated framework. Which of the following options is not correct about ERM?

选项:

A.

The level of capital a firm holds below the minimum regulatory requirements is the most visible expression of its risk appetite.

B.

At the ERM level, risk appetite is typically expressed in overarching statements and criteria.

C.

Regulators consider risk culture to be a key driver of ERM framework effectiveness.

D.

The firm will accept the project only when the project's return is larger than the contribution cost of the project to the firm's total risk.

解释:

A is correct.

考点:Enterprise Risk Management Structure

解析:一家公司持有高于(而非低于)最低监管要求的资本水平是其风险偏好的最明显表现。

如题

1 个答案
已采纳答案

李坏_品职助教 · 2023年11月04日

嗨,从没放弃的小努力你好:


题目问的是关于ERM的叙述中哪一个是错误的。


A选项:一家公司持有的低于最低监管要求的资本水平是其风险偏好的最明显表现。这个错了,应该是高于最低监管要求的资本水平才是风险偏好的最佳表现。


B:在ERM中,风险偏好通过总体风险的叙述(董事会主要负责)+具体风险标准来进行阐述。这个叙述没什么问题。

C:监管者认为风险管理文化是影响ERM效率的关键因素。也是对的。

D:公司只有在项目的回报率大于项目的风险成本贡献率的时候才投资这个项目。ERM要求公司从风险调整后的收益的角度,来考察项目。如果这个项目的收益率是5%(假设能带来50万美元的收益),但是它会增加公司100万美元的风险,那这个项目是不划算的。D正确。





----------------------------------------------
虽然现在很辛苦,但努力过的感觉真的很好,加油!

  • 1

    回答
  • 0

    关注
  • 286

    浏览
相关问题

NO.PZ2019052001000007 问题如下 Enterprise risk management(ERM)is the process of managing all corporation risks within integrateframework. Whiof the following options is not one of the contents of ERM? A.Risk assessment for every projeshoulcentralize B.The planner of the projeconcts a preliminary assessment of the projerisks. C.Regularly assess the performanof eabusiness unit anmeasure the impaof eabusiness unit on the totrisk. The firm will accept the projeonly when the project's return is larger ththe contribution cost of the projeto the firm's totrisk. A is correct.考点Effective ERM的特点解析ERM要求的是centralizing risk management, 是为了保障每个项目的总风险都被项目经理在内部评估中完整的评估出来。集中评估不满足这个目的。 如题

2022-11-15 06:10 1 · 回答

老师好,看了之前其他同学的提问和解答,能理解基础班讲义第259页提到了centralize下图1标黄)。但是在基础班讲义第249页同时也提到了传统的risk management, 才是把每一个风险分开单独看待,我理解即为centralize下图2标黄);同时,在基础班讲义第250页,也提到了ERM是centralizerisk management (下图3标黄)。能不能请老师再详细的讲一下ERM下,什么时候要用centralize什么时候用 centralize

2021-01-01 16:37 1 · 回答

请问什么意思,还有A我不能理解为什么整体是Top-wn的过程的ERM却是去中心化的呢?

2020-10-26 17:37 1 · 回答

老师好,能否帮忙对比讲解一下这道题的A答案,以及下面这道题的C答案。下面这道题是Section 4的题目。谢谢!

2020-07-18 21:11 1 · 回答