4. The best responses that Velasquez can make to Question 1 and Question 2 are:
选项:
解释:
A is correct.
Projects with shorter paybacks do not necessarily have a positive NPV. For mutually exclusive projects, the NPV and IRR criteria will not necessarily provide the same project ranking.
payback criterion指的是投资回收期,我记得自己原来上学时经济学,学过的回收期都是考虑折现的。所以,如果到了回收期,一般NPV都是大于o的