开发者:上海品职教育科技有限公司 隐私政策详情

应用版本:4.2.11(IOS)|3.2.5(安卓)APP下载

CFApipa · 2022年08月13日

老师所以这道题考的是flotation method2的知识点是吗?

NO.PZ2016021706000031

问题如下:

Adam Company is planning to invest in a project with a $100,000 initial cash outlay. This new project is expected to generate cash flows of $30,000 every year in the next ten years. The flowing is the information of Adam company:

Adam Company will finance the project with a debt-to-equity ratio of 1.5. The dollar amount of flotation costs is $3000 for the equity of this project.

If floatation costs are incorporated as an adjustment to the initial-period cash flows, what's the NPV for the project?

选项:

A.

$90,039.

B.

$91,236.

C.

$100,030.

解释:

B is correct.

Re = 2.5/50+ 0.05= 10%

D/E=1.5, Wd=60%, We=40%

WACC = 0.60*0.08 + 0.40*0.1 = 8.8%

N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275

NPV = -$103000+$194236.275 = $91236.275.

老师所以这道题考的是flotation method2的知识点是吗? 所以只要题目说flotation cost 是个具体的金额,就是考察 method 2 也就是preferred approach?



1 个答案

王琛_品职助教 · 2022年08月14日

嗨,从没放弃的小努力你好:


1)老师所以这道题考的是flotation method2的知识点是吗?

是的

2)所以只要题目说flotation cost 是个具体的金额,就是考察 method 2 也就是preferred approach?

并不是这么绝对哈,还得具体看题目已知的条件

比如这道题,其实使用 method 1 也可以做的,只不过题目要求使用 method 2 而已

3)

其实就同学问的这道题而言,我们并没有收录到经典题,因为这道题的计算量还是有点大的,而考试一般都是短平快

关于发行成本的考查角度,我们在经典题中已经把目前能覆盖的经典题目都放上啦,同学只要把经典题里的题目掌握即可哈

----------------------------------------------
努力的时光都是限量版,加油!

  • 1

    回答
  • 0

    关注
  • 320

    浏览
相关问题

NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 我不太能理解为什么第一步的Re是用2.5/50+0.05,请问这是在哪里学的?

2022-10-14 18:01 1 · 回答

NO.PZ2016021706000031问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039.B.$91,236.C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 老师我想问一问,这道题能不能用计算机cf的功能来算出来,只不过是CF0是10300,剩下的I是Wacc这样,谢谢

2022-10-03 10:43 1 · 回答

NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costs is $3000 for the equity of this project. If floatation costs are incorporateaustment to the initial-periocash flows, what's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 这道题感觉有点问题根据债和股的比例能知道股占了40%,总共投入了10w那么能算出多少股股数知道了能算出f,不就应该用f那个公式而不是r=P +G

2022-08-29 23:22 1 · 回答

NO.PZ2016021706000031 问题如下 Am Company is planning to invest ina projewith a $100,000 initicash outlay. This new projeis expecteto generatecash flows of $30,000 every yein the next ten years. The flowing is theinformation of Am companyAm Company will finantheprojewith a bt-to-equity ratio of 1.5. The llamount of flotation costis $3000 for the equity of this project. What's the NPV for the project? A.$90,039. B.$91,236. C.$100,030. B is correct.Re = 2.5/50+ 0.05= 10%E=1.5, W60%, We=40%WA= 0.60*0.08 + 0.40*0.1 = 8.8%N=10, I/Y=8.8, PMT=30000, FV=0, CPT PV=194236.275NPV = -$103000+$194236.275 = $91236.275. 为什么这里的分母50,不需要减去F?不是应该2.5/50-3000+0.05吗

2022-08-08 23:36 1 · 回答